Pre-cast-structural-beam-thumbnail

Design Optimisation of Pre-Cast Support Beams

An FEA investigation into pile and beam systems was undertaken for a client to improve a 10 year old design and increase its cost effectiveness for good ground conditions. This was achieved by reducing the reinforcement in the beams inherited from previous over-design and eliminating unecessary tie beams within the masonry structure while retaining performance.

Overview

  • Work performed on behalf of Roger Bullivant Limited.
  • Existing design for pre-cast pile and beam foundation system for housing
  • Introduced in early 1990’s
  • Used in poor to marginal ground conditions
  • Proved successful, currently 50 houses per week
  • Existing design not cost-effective for good ground conditions

System Components

Known Conservatisms

  • Existing design known to be unduly conservative
  • Design calculations based on assumption of simply supported beams
  • Full load of walls, floor and roof imposed as a UDL
  • Bending moment = WL2/8
  • Shear Force = WL/2
  • Work by Building Research Station in 1950’s identified this approach as conservative as no account is taken of stiffness of masonry
  • Conservatisms therefore relate to load paths and the interaction between the masonry superstructure and the supporting sub-structure of support beams and pile caps

Loading

  • Load is attracted to piles due to:
    • Arching effect of masonry
    • Greater stiffness of support points
  • Hence load is less than UDL at centre span
  • Some moment restraint is offered at beam supports
  • Extent of these effects difficult to quantify

Project Objectives

  • To reduce the reinforcement in the beams to eliminate the over-design previously identified.
  • To demonstrate that piles supporting a masonry structure do not need to be restrained in two directions by beams even when placed out of position, and therefore to eliminate unnecessary tie beams.
  • To eliminate reinforcement cast into the ends of the beams to form the connections.
  • To investigate different bearing lengths between cap and beams to allow the beam to be cast in incremental stock lengths.

Project Stages

Initial Test House

Key Design Aspects

  • Constructed prior to use of FEA
  • Spans of up to 5m
  • Substantial reduction in levels of reinforcement
  • Maximum design loads applied
  • Removal of steel at joints

Results

  • Separation at Damp Proof Course level
  • Cracking of brick and blockwork

Benefits of FEA

  • A more accurate prediction of the true load paths.
  • A reduction in the number of conservative approximations needed in design calculations.
  • An examination of the effects of different designs, boundary conditions and loading situations with (comparative) ease.
  • An ability to investigate the robustness of the design to potential “hazards” (for example, the unforeseen catastrophic failure of a supporting pile).

FEA Modelling Methods

  • Double layers of shell elements for walls
  • Wall ties using beam elements
  • Support beams modelled with beam elements, with cross-section defined explicitly
  • Embedded reinforcements in beam elements
  • Multiple fixed crack model for concrete
  • DPC represented with interface gap elements

Initial Results

  • Prediction of cracks at DPC level with size and disposition showing good agreement with test
  • Areas where stresses in masonry exceeded likely tensile strength showed good agreement with size and location of observed cracks
  • Cracks predicted to occur on beams in locations and of an extent that corresponded well with cracks observed on test beams

Decision For Further Actions

  • Use FEA to investigate further the effects of various possible design modifications
  • Derive a new test house layout
  • Analyse the new test house layout, with various sensitivity studies
  • Construct a new test house, and monitor it fully during a comprehensive loading sequence.

Layout Features

  • Large garage
  • Typical door and window layout from detached and semi-detached houses
  • Large party wall
  • Large patio door
  • Opening included post-construction
  • Modified beam connections
  • Omission of tie beams
  • Reduction in maximum beam span

Sensitivity Studies

  • Zero lateral restraint at pile locations, compared with full lateral restraint.
  • Variations in material properties.
  • The inclusion of future openings.
  • Piles being placed away from their intended position.
  • The connections between the beams being unable to develop sufficient hogging capacity, allowing a “plastic hinge” to be formed.

Analysis Results

  • Beam forces and moments for design purposes
  • Displacements
  • Minimal cracking of beams
  • No more than hairline cracks at DPC level
  • Low probability of significant cracking in masonry

Comparison with Strip Footing

  • Simplified analysis for comparison
  • Same house superstructure supported on Winkler spring representation
  • Likelihood of masonry cracking predicted to be at least as great as that from kit T-beam foundation system

Design Methods

  • Design calculations as per BS8110: Part 1: 1997
  • Design of suitable beam cross-sections arrived at through iterative process
  • Final forces and moments ~40% of those based on UDL
  • Hogging moment capability at joints by use of top steel

Testing & Monitoring

  • Full scale test house constructed
  • Loaded with full design load
  • Load applied in phases to investigate all potential load imbalances etc.
    Behaviour of structure fully monitored by CERAM Building Technology
  • Displacements monitored and crack surveys carried regularly during entire loading process and subsequently as structure left at full load
  • Strain gauges used at potential crack locations
  • Precision levelling

Comparison of Test & Analysis

  • No significant cracks or displacements observed during testing
  • Displacements of similar order to predictions but too small to make accurate comparisons possible
  • No distress to structure despite significant loading

Conclusions

  • FEA used in combination with test programme
  • FEA substantially reduced amount of testing required
  • FEA allowed design to be optimized resulting in significant cost savings
  • Environmental benefits from reduced use of materials
  • Unnecessary conservatisms substantially reduced
  • Final design proven by testing
  • BBA approval granted for revised system
  • Design optimization of pre-cast components is an ideal application for advanced FE methods

October 1998

Related Technology

Related Software

Related Applications

Related Industries