Design Optimisation of Pre-Cast Support Beams
An FEA investigation into pile and beam systems was undertaken for a client to improve a 10 year old design and increase its cost effectiveness for good ground conditions. This was achieved by reducing the reinforcement in the beams inherited from previous over-design and eliminating unecessary tie beams within the masonry structure while retaining performance.
Overview
- Work performed on behalf of Roger Bullivant Limited.
- Existing design for pre-cast pile and beam foundation system for housing
- Introduced in early 1990’s
- Used in poor to marginal ground conditions
- Proved successful, currently 50 houses per week
- Existing design not cost-effective for good ground conditions
System Components
Known Conservatisms
- Existing design known to be unduly conservative
- Design calculations based on assumption of simply supported beams
- Full load of walls, floor and roof imposed as a UDL
- Bending moment = WL2/8
- Shear Force = WL/2
- Work by Building Research Station in 1950’s identified this approach as conservative as no account is taken of stiffness of masonry
- Conservatisms therefore relate to load paths and the interaction between the masonry superstructure and the supporting sub-structure of support beams and pile caps
Loading
- Load is attracted to piles due to:
- Arching effect of masonry
- Greater stiffness of support points
- Hence load is less than UDL at centre span
- Some moment restraint is offered at beam supports
- Extent of these effects difficult to quantify
Project Objectives
- To reduce the reinforcement in the beams to eliminate the over-design previously identified.
- To demonstrate that piles supporting a masonry structure do not need to be restrained in two directions by beams even when placed out of position, and therefore to eliminate unnecessary tie beams.
- To eliminate reinforcement cast into the ends of the beams to form the connections.
- To investigate different bearing lengths between cap and beams to allow the beam to be cast in incremental stock lengths.
Project Stages
Initial Test House
Key Design Aspects
- Constructed prior to use of FEA
- Spans of up to 5m
- Substantial reduction in levels of reinforcement
- Maximum design loads applied
- Removal of steel at joints
Results
- Separation at Damp Proof Course level
- Cracking of brick and blockwork
Benefits of FEA
- A more accurate prediction of the true load paths.
- A reduction in the number of conservative approximations needed in design calculations.
- An examination of the effects of different designs, boundary conditions and loading situations with (comparative) ease.
- An ability to investigate the robustness of the design to potential “hazards” (for example, the unforeseen catastrophic failure of a supporting pile).
FEA Modelling Methods
- Double layers of shell elements for walls
- Wall ties using beam elements
- Support beams modelled with beam elements, with cross-section defined explicitly
- Embedded reinforcements in beam elements
- Multiple fixed crack model for concrete
- DPC represented with interface gap elements
Initial Results
- Prediction of cracks at DPC level with size and disposition showing good agreement with test
- Areas where stresses in masonry exceeded likely tensile strength showed good agreement with size and location of observed cracks
- Cracks predicted to occur on beams in locations and of an extent that corresponded well with cracks observed on test beams
Decision For Further Actions
- Use FEA to investigate further the effects of various possible design modifications
- Derive a new test house layout
- Analyse the new test house layout, with various sensitivity studies
- Construct a new test house, and monitor it fully during a comprehensive loading sequence.
Layout Features
- Large garage
- Typical door and window layout from detached and semi-detached houses
- Large party wall
- Large patio door
- Opening included post-construction
- Modified beam connections
- Omission of tie beams
- Reduction in maximum beam span
Sensitivity Studies
- Zero lateral restraint at pile locations, compared with full lateral restraint.
- Variations in material properties.
- The inclusion of future openings.
- Piles being placed away from their intended position.
- The connections between the beams being unable to develop sufficient hogging capacity, allowing a “plastic hinge” to be formed.
Analysis Results
- Beam forces and moments for design purposes
- Displacements
- Minimal cracking of beams
- No more than hairline cracks at DPC level
- Low probability of significant cracking in masonry
Comparison with Strip Footing
- Simplified analysis for comparison
- Same house superstructure supported on Winkler spring representation
- Likelihood of masonry cracking predicted to be at least as great as that from kit T-beam foundation system
Design Methods
- Design calculations as per BS8110: Part 1: 1997
- Design of suitable beam cross-sections arrived at through iterative process
- Final forces and moments ~40% of those based on UDL
- Hogging moment capability at joints by use of top steel
Testing & Monitoring
- Full scale test house constructed
- Loaded with full design load
- Load applied in phases to investigate all potential load imbalances etc.
Behaviour of structure fully monitored by CERAM Building Technology - Displacements monitored and crack surveys carried regularly during entire loading process and subsequently as structure left at full load
- Strain gauges used at potential crack locations
- Precision levelling
Comparison of Test & Analysis
- No significant cracks or displacements observed during testing
- Displacements of similar order to predictions but too small to make accurate comparisons possible
- No distress to structure despite significant loading
Conclusions
- FEA used in combination with test programme
- FEA substantially reduced amount of testing required
- FEA allowed design to be optimized resulting in significant cost savings
- Environmental benefits from reduced use of materials
- Unnecessary conservatisms substantially reduced
- Final design proven by testing
- BBA approval granted for revised system
- Design optimization of pre-cast components is an ideal application for advanced FE methods
October 1998



